Item | Amount | Description |
---|---|---|
Vortex Filters | $1,280 | Main filters |
Demo hammer and bits | $850 | The tool |
Tree removal | $550 | The rubber tree |
PVC fittings and gate valves | $180 | 4" plumbing parts |
Lumber | $55 | For wall bracing |
Concrete Mixer | $355 | Better than renting |
Concrete blocks and concrete | $355 | For filter walls |
Second load of Concrete | $328 | For filter walls |
Day laborers | $185 | Help with digging |
Dirt and rubble removal | $1,500 | Hauled away |
Third load Concrete and blocks | $328 | For slab of main |
Total | $4,138 | . |
I'm afraid there is a lot more to add before it is finished.